June 13, 2003
| The Space Saver crew continues their work on the basement level. Holes are drilled in the floor to set the shelving rails and adjust their height. Using laser sights they level the rails the compact shelving will be placed upon. After adjusting the screws to the correct height, a hydraulic cement is poured underneath the line of rail. Excess is troweled off and the cement is left to harden. |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| Photos by Chad Hopman. |
|